In which phase of the SDLC should security controls be implemented when training users on information protection and recognizing social engineering attacks?

  1. Planning

  2. Design

  3. Implementation

  4. Testing

The correct answer is: Implementation

The correct phase of the Software Development Life Cycle (SDLC) for implementing security controls related to training users on information protection and recognizing social engineering attacks is the implementation phase. During this phase, the actual code and components of the system are developed and deployed, and it becomes critical to ensure that users are educated on how to interact with the system securely. When security controls are implemented, it’s vital to provide training so that users understand their responsibilities in protecting information and can identify potential threats, such as social engineering tactics. This training helps create a security-conscious culture and equips users with the knowledge to mitigate risks as they arise in their interactions with the system. In the planning phase, while initial security requirements may be identified, no direct user training occurs at this stage. The design phase focuses on outlining the architecture and security measures but does not typically involve user training or direct implementation of security controls. During the testing phase, the focus is primarily on assessing the security and functionality of the system rather than educating the users. Therefore, the implementation phase is where security awareness and training ensure that the users are prepared to handle confidential information securely and recognize potential threats effectively.